Standard lead time for a part #8371
-
In my use case, it would be helpful to have a concept of a lead time so I could know how long to order and assemble an assembly depending on what parts of the build are still remaining to be purchased. Is this a concept currently available in Inventree? I searched around and could only find a context variable in the Supplier Part docs page but I don't think that's accessible to a front end user. Curious if others have a similar use case or know of a way to solve this problem. Thanks all :) |
Beta Was this translation helpful? Give feedback.
Replies: 2 comments 2 replies
-
@wolffam this has been discussed but not yet implemented. It would be a good addition, although I think an early implementation would just be to add the field to the Is this something that you would be interested in helping to develop, or alternatively fund? |
Beta Was this translation helpful? Give feedback.
-
Hi, we would be interested in this feature too. We are willing to participate in the development or the funding too. How is the procedure for that? Sorry, I'm new in this, so I have not an idea of the procedure. |
Beta Was this translation helpful? Give feedback.
@wolffam this has been discussed but not yet implemented. It would be a good addition, although I think an early implementation would just be to add the field to the
SupplierPart
model and add some basic front-end support.Is this something that you would be interested in helping to develop, or alternatively fund?