Deadline: 20.06.2022
gantt
title Zeitplan Budget Binder
dateFormat YYYY-MM-DD
excludes weekends
section Grundgeruest bauen
Multiplattform Compose :active, 2022-04-04, 2022-04-08
Ktor Client + asyncron :2022-04-11, 2022-04-22
Abfragen von APIs testen :2022-04-25, 2022-04-29
section UI/UX Entwicklung
LoFi Prototyp entwickeln :active, 2022-04-04, 2022-04-22
User Tests :2022-04-25, 2022-04-29
section Backend
Datenmodell :2022-05-02, 2022-05-06
Schnittstellen :2022-05-09, 2022-05-13
RestAPI bauen :2022-05-16, 2022-05-20
Test der API :2022-05-16, 2022-05-20
section Frontend
Web Frontend :2022-05-02, 2022-06-20
Desktop Frontend :2022-05-02, 2022-06-20
Android Frontend :2022-05-02, 2022-06-20
iOS Frontend :2022-05-02, 2022-06-20
Frontend User Tests :2022-05-02, 2022-06-20
section Dokumentation
Dokumentieren :2022-06-01, 2022-06-20