10 changes: 5 additions & 5 deletions gannt.puml
Original file line number Diff line number Diff line change
Expand Up @@ -12,22 +12,22 @@ Project starts 2024-02-15
--Requirements Gathering--
[Review brief] requires 2 days and is colored in sandybrown/black
then [Research] requires 5 days and is colored in sandybrown/black
then [Draft potential questions] on {Lucy}{Tim}{Zac}{Lia} requires 28 days and is colored in sandybrown/black
then [Draft potential questions] on {Lucy:14}{Tim:14}{Zac:14}{Lia:14}{Liam:14}{Kai:14}{Sammy:14} requires 6 days and is colored in sandybrown/black

[Customer Meeting] on {Lucy}{Tim}{Sammy}{Zac} happens at [Draft potential questions]'s end and is colored in sandybrown/black
then [Write up Requirements] on {Lucy}{Zac}{Lia} requires 21 days and is colored in sandybrown/black and is 0% complete
then [Write up Requirements] on {Lucy:33}{Zac:33}{Lia:33} requires 6 days and is colored in sandybrown/black and is 0% complete
[Write up Requirements] is 20% complete

--Design--
[Design Architecture] on {Liam}{Lia}{Kai}{Sammy} starts at 2024-02-29 and requires 28 days and is colored in yellowgreen/black
[Design Architecture] on {Liam:25}{Lia:25}{Kai:25}{Sammy:25} starts at 2024-02-29 and requires 7 days and is colored in yellowgreen/black
[Design Architecture] is 0% complete
[Risk Assessment] on {Kai}{Zac} starts at 2024-02-29 and requires 14 days and is colored in yellowgreen/black
[Risk Assessment] on {Kai:50}{Zac:50} starts at 2024-02-29 and requires 7 days and is colored in yellowgreen/black
[Risk Assessment] is 30% complete
[Design Map] on {Lia} starts at 2024-02-29 and requires 3 days and is colored in yellowgreen/black
[Design Map] is 0% complete
then [Design Characters] on {Lia} requires 4 days and is colored in yellowgreen/black
[Design Characters] is 0% complete
[Method Selection] on {Tim}{Sammy} starts at 2024-02-29 and requires 14 days and is colored in yellowgreen/black
[Method Selection] on {Tim:50}{Sammy:50} starts at 2024-02-29 and requires 7 days and is colored in yellowgreen/black
[Method Selection] is 10% complete

--Implementation--